Recently, the Ningxia-Hunan ± 800 kV UHV DC transmission project (Hunan section) foundation first pilot activity was held in Changde, marking the official start of the basic project of the line. The overall goal of the project is to implement standardized construction and build a "safe and reliable, independent innovation, economical and reasonable, environmentally friendly, and world-class" high-quality power project to ensure a successful operation and long-term safe operation. For this reason, the KR110D electric construction drilling rig of TYSIM Leasing Company is selected for the mechanized foundation construction of the project to ensure the safe and stable completion of the project with good quality and quantity.

"Ningdian into Hunan" project has a profound impact on the two provinces of Ningxiang

"Ningdian into Hunan", that is, Ningxia-Hunan ± 800 kV UHV DC transmission project is my country's first UHV DC project sent out from the Shage base. The project construction will effectively improve Hunan's power supply guarantee capacity by bringing together Ningxia's new energy power and sending it to Hunan's load center with a rated voltage of ± 800 kV and a transmission capacity of 8 million kilowatts. At the same time, it is of great significance to promote the development of new energy resources in Ningxia, promote the clean and low-carbon transformation of energy, strengthen the power supply guarantee, help the economic and social development of Ningxia and Hunan, and serve the carbon peak and carbon neutral goals.

TYSIM Electric Construction Drilling Rig Joining in Foundation First Foundation Pilot Work

After careful site survey, the project selected N4882 leg a to be mechanically drilled by electric construction drilling rig, leg B finished product display, leg c reinforcement cage installation, leg d lock wall protection. Mechanized foundation construction selects TYSIM KR110D electric construction drilling rig, one of the "five brothers" of electric construction. Its main features are light weight of the main machine, strong climbing ability, large pile diameter, high rock entry efficiency, continuous operation in all-weather and all-weather environment, and effectively reduce the construction safety risk in the process of foundation pit excavation.

Major power construction projects must have power construction "five brothers" figure

In the past, the construction of the line tower foundation in the construction of the power grid relied heavily on manpower, and its engineering was extremely difficult and dangerous in various terrain such as inland mountainous areas and paddy fields. Due to the lack of professional and efficient customized pile machine companies in the industry, the development goal of "fully mechanized construction" put forward by State Grid Group eight years ago has not been achieved.

To this end, TYSIM Foundation's parent company, TYSIM Machinery, through four years of hard work, has traveled to various construction sites in more than 10 provinces across the country and has successively developed and customized five models for the State Grid Group, which is called the "Five Brothers of Electric Power Construction" by the State Grid Group ". Those projects that used to have no equipment available and relied on manual teams to complete a tower base in a month were completed within three days after the equipment was in place. According to the feedback from the construction party of the project, the "Five Brothers of Power Construction" has high operation efficiency, safety and reliability. Compared with the traditional manual excavation method, it not only greatly improves the work efficiency and shortens the construction period, but also reduces the construction risk level and reduces labor. Input ensures personal safety.